CompTIA Project+ (PK0-005) · Domain 1 · 33% of exam

Project Management Concepts

Drill 20 practice questions focused entirely on Project Management Concepts for the CompTIA PK0-005 exam. Tap an answer for instant feedback and a full explanation — no sign-up, always free.

Verified answer20 questions
Question 1 of 20

A software team using Scrum is midway through a project. The project manager wants to forecast how much work the team can realistically complete in upcoming sprints so the sponsor can be given a credible delivery projection. Which metric should the project manager rely on for this forecast?

Reviewed for accuracy · Report an issue
Question 2 of 20

During planning for a data center migration, the project manager identifies a high-probability, high-impact risk: performing the cutover during the company's peak sales season could cause catastrophic revenue loss if the migration fails. After discussion, the team decides to reschedule the entire cutover to occur after the sales season ends, eliminating any chance of this risk affecting the peak period. Which negative risk response strategy does this represent?

Reviewed for accuracy · Report an issue
Question 3 of 20

A project manager on an agile software project wants a simple visual that shows the team how much work remains in the current sprint compared to the ideal pace needed to finish on time. Which artifact should the project manager use to communicate this to the team during the sprint?

Reviewed for accuracy · Report an issue
Question 4 of 20

During execution of a predictive project, a stakeholder submits a formal request to add a new reporting feature that would increase both cost and schedule. The project manager has already logged the request. What should the project manager do NEXT before any work on the change begins?

Reviewed for accuracy · Report an issue
Question 5 of 20

During a project retrospective, two lead engineers strongly disagree about which database platform to adopt. Rather than picking a side or splitting the difference, the project manager facilitates a working session where both engineers share their underlying requirements, and together the team designs a solution that satisfies both sets of concerns. Which conflict resolution technique is the project manager using?

Reviewed for accuracy · Report an issue
Question 6 of 20

A project manager is assembling a team for a highly complex, time-sensitive product launch that will require constant collaboration and rapid problem-solving among developers, designers, and QA testers. The organization has office space available and asks the PM whether to place the team in one shared physical location or allow them to work independently from separate buildings. Which is the PRIMARY benefit the PM should cite in favor of a collocated team?

Reviewed for accuracy · Report an issue
Question 7 of 20

A project team currently has 6 members, all of whom communicate directly with one another. The sponsor authorizes adding 4 more team members to accelerate delivery. The project manager is concerned about the increased complexity of communication. Approximately how many total communication channels will exist after the new members join?

Reviewed for accuracy · Report an issue
Question 8 of 20

A vendor supporting your project has informed you verbally that they need to adjust a contractual deliverable date that will affect the project's legally binding agreement. As the project manager, you need to document this change and ensure both organizations have an official, authoritative record for potential future disputes. Which communication method is MOST appropriate?

Reviewed for accuracy · Report an issue
Question 9 of 20

Two functional managers on a project disagree over how a shared testing lab should be scheduled. Neither will get full access to the lab during the critical testing window. After discussion, the project manager helps them agree that each team gets the lab for half the available days, with both giving up some of what they originally wanted so the project can move forward. Which conflict resolution technique did the project manager use?

Reviewed for accuracy · Report an issue
Question 10 of 20

Two engineers on your project disagree about which database technology to use. Rather than picking a side quickly, you gather both engineers, review the performance requirements, benchmark data, and long-term maintenance costs together, then reach a decision supported by the evidence. Which conflict resolution technique are you using?

Reviewed for accuracy · Report an issue
Question 11 of 20

Halfway through a predictive project, the project manager reviews earned value data. The budget at completion (BAC) is $200,000. The earned value (EV) is $90,000, the actual cost (AC) is $110,000, and the planned value (PV) is $100,000. What does this data tell the project manager about the project's cost performance?

Reviewed for accuracy · Report an issue
Question 12 of 20

A predictive software deployment project is running two weeks behind on a critical-path activity, and the delivery deadline cannot move because it is tied to a contractual milestone. The project manager has budget available and decides to add two experienced developers to the delayed task to bring it back on schedule. Which schedule compression technique is the project manager using?

Reviewed for accuracy · Report an issue
Question 13 of 20

You are managing a software project using an agile approach. Each morning the development team gathers for 15 minutes so each member states what they completed yesterday, what they will work on today, and any blockers preventing progress. Which purpose does this recurring meeting primarily serve?

Reviewed for accuracy · Report an issue
Question 14 of 20

A newly formed project team includes members from three departments who have never worked together. During the first week, disagreements arise over how decisions should be made, how often the team should meet, and who is responsible for updating shared documents. The project manager wants to prevent these recurring disputes and set clear expectations for how the team will operate together. What should the project manager create to address this?

Reviewed for accuracy · Report an issue
Question 15 of 20

During a project, two senior engineers strongly disagree about whether to use a new database platform. The debate has stalled a critical safety-related deliverable, and a regulatory deadline is only two days away. The project manager has listened to both positions, but there is no time left for consensus. Which conflict resolution technique should the project manager apply?

Reviewed for accuracy · Report an issue
Question 16 of 20

A project manager is building the schedule for an office relocation. Task B (install network cabling) cannot begin until Task A (complete electrical work) is finished, and Task C (set up workstations) cannot begin until Task B is done. The PM needs a tool that visually displays these task dependencies along a timeline so the team can see how a delay in one task affects the others. Which scheduling tool best meets this need?

Reviewed for accuracy · Report an issue
Question 17 of 20

During a software development project, a developer proudly informs the project manager that she added several extra features to a module because she 'had time' and thought the client would appreciate the polish. These features were not requested and are not in the approved scope. What is the BEST way for the project manager to characterize this situation?

Reviewed for accuracy · Report an issue
Question 18 of 20

A project involves building a new data center facility with strict regulatory requirements and fixed construction deadlines, while simultaneously developing custom monitoring software whose features stakeholders expect to refine throughout the effort. The project manager must select an approach that suits both work streams. Which methodology is the BEST fit for this project?

Reviewed for accuracy · Report an issue
Question 19 of 20

A project manager is planning a data center migration and identifies a risk that a critical hardware component could fail during the cutover, causing extended downtime and significant financial penalties. Rather than attempting to prevent the failure entirely, the PM decides to purchase an insurance policy and a vendor support contract that covers replacement costs and rapid onsite service if the failure occurs. Which risk response strategy is the project manager using?

Reviewed for accuracy · Report an issue
Question 20 of 20

A support team handles a steady stream of unpredictable maintenance requests that arrive individually throughout the day, with no fixed release dates. The project manager wants an approach that visualizes work in progress, limits how many items are worked on at once to avoid overloading the team, and allows continuous delivery as each item completes. Which method best fits these needs?

Reviewed for accuracy · Report an issue