Question 149 of 149

During the execution phase of a software deployment project, a team member reports to the project manager: '17 test cases were completed today, and 3 failed.' The project manager needs to convert this into something useful for the weekly stakeholder status report. What must the project manager do with this raw measurement before it becomes meaningful for reporting?