CompTIA Project+ (PK0-005)148 / 149
Question 148 of 149

A team member reviewing a work package on the WBS is unsure exactly what deliverables it includes, what the acceptance criteria are, and which resources are assigned. The project manager wants to point the team member to a single document that provides this detailed, granular information for each WBS component. Which document should the project manager reference?