Question 142 of 149

A project manager on an agile team needs to give stakeholders a realistic forecast of how many sprints remain to complete the product backlog. The team has completed four sprints, and the PM has recorded the number of story points finished in each. Which combination of artifacts should the PM use to produce this forecast?