CompTIA Project+ (PK0-005)139 / 149
Question 139 of 149

Midway through a predictive project, the customer requests adding three new features to the deliverable. The project manager confirms the budget and the final delivery date cannot change. Based on the triple constraint, what is the most likely consequence the project manager must communicate to the customer?