CompTIA Project+ (PK0-005)138 / 149
Question 138 of 149

A project manager is monitoring a software rollout that is currently over budget. The sponsor insists the project must still be completed within the original approved budget (BAC). To assess whether this is realistic, the project manager wants to calculate the cost efficiency the team must achieve on the remaining work to meet that budget target. Which metric should the project manager calculate?