Question 136 of 149

During planning, a project manager is estimating the duration of a complex integration task. The technical lead provides an optimistic estimate of 8 days, a most likely estimate of 14 days, and a pessimistic estimate of 32 days. The PM wants a weighted duration estimate that reduces the influence of the extreme values. Which value should the PM use?