A project has consumed $400,000 of its $500,000 budget, but a recent market shift means the product will no longer meet customer needs and cannot be sold. Completing the remaining work will cost another $100,000, and the finished product is now expected to generate no revenue. Reworking the concept would require a new $250,000 project that is forecast to generate $600,000 in revenue. What should the project manager recommend to the sponsor?