Question 132 of 149
A project manager is engaging an external vendor to build a custom reporting module. The vendor needs a document that specifies the exact deliverables, tasks, timeline, and acceptance criteria for the work to be performed under the existing master agreement. Which procurement document should the project manager prepare?