Question 126 of 149

Midway through a predictive infrastructure project, the team identifies a critical risk that would require an additional $75,000 outside the approved budget to mitigate. The project manager has assembled the mitigation plan and cost estimate. To whom should the project manager escalate to obtain the additional funding and formal authorization to proceed?