Question 125 of 149

During a project to deploy a new analytics platform, the project manager discovers that the team plans to install a commercial reporting tool on 50 workstations, but the organization only holds licenses for 20 seats. The vendor's licensing terms prohibit exceeding purchased seats. What should the project manager do FIRST to address this governance and compliance concern?