CompTIA Project+ (PK0-005)124 / 149
Question 124 of 149

During a design review, two senior developers begin a heated disagreement about a technical approach. The project manager notices the conflict is minor and unrelated to the immediate agenda item, and the review must finish within the next 15 minutes to stay on schedule. The PM emphasizes the areas the developers agree on and downplays the differences so the meeting can continue, planning to address the underlying issue afterward. Which conflict resolution technique is the PM using?