CompTIA Project+ (PK0-005)123 / 149
Question 123 of 149
A project manager is finalizing a cloud hosting arrangement for a new customer-facing application. The business requires a documented guarantee that the vendor will maintain 99.9% system availability, with defined penalties if the vendor fails to meet that threshold. Which procurement document should the project manager ensure contains this performance guarantee?
Reviewed for accuracy · Report an issueNext question