Question 122 of 149

A project manager is finalizing a support contract with a managed services vendor for a new customer-facing application. The business owner insists that any critical outage must be fully fixed within two hours. The vendor's proposed agreement guarantees that a technician will begin working on critical incidents within 15 minutes of a report. Which contract term does the vendor's proposed guarantee actually define, and what should the PM do?