🔥 3-day streak
CompTIA Project+ (PK0-005)120 / 149
Question 120 of 149

A project manager is negotiating a hosting agreement with a cloud vendor for a customer-facing application. The vendor's proposed SLA guarantees 99.9% monthly uptime. The project manager wants to ensure that if the vendor fails to meet this uptime commitment, the organization is compensated without having to pursue formal legal action. Which SLA element should the project manager insist on including?

Reviewed for accuracy · Report an issueNext question