Question 116 of 149
Midway through a predictive software implementation project, a key business stakeholder emails the project manager directly and asks to add a new reporting module because 'it's small and won't take long.' The scope baseline has already been approved and the project is currently on schedule and budget. What is the project manager's BEST first action?