A project manager is halfway through a construction project and reviews the earned value data. The planned value (PV) at this point is $200,000, the earned value (EV) is $170,000, and the actual cost (AC) is $165,000. The sponsor asks whether the project is ahead of or behind schedule. Which conclusion should the project manager report?