CompTIA Project+ (PK0-005)112 / 149
Question 112 of 149

During a scheduled production release of a new payroll module, the project team discovers that a critical integration with the existing HR database is returning errors. Payroll processing is due to run in six hours, and the failing integration cannot be fixed in time. Which action should the project manager direct the team to take FIRST?