CompTIA Project+ (PK0-005)111 / 149
Question 111 of 149

A project manager implements a risk response by outsourcing a specialized data migration to a third-party vendor to reduce the chance of technical failure. During planning, the team realizes that relying on the vendor introduces a new concern: the vendor may miss the delivery deadline, delaying the project. How should the project manager classify and handle this new concern?