CompTIA Project+ (PK0-005)109 / 149
Question 109 of 149

During planning for a data center migration, the project manager and team identify several risks that cannot be avoided or transferred, such as potential hardware failures during the physical move. The sponsor asks how the project will financially prepare for these known risks if they occur. What should the project manager establish to address this?