A project manager discovers that two of the developers assigned to critical tasks on the schedule are also committed 60% of their time to another department's operational work. The functional managers were never formally consulted about the availability of these resources. Which document, if it had been properly created and agreed upon, would MOST likely have prevented this over-allocation issue?