Question 99 of 149
A project manager for a software rollout notices that defects are being caught late, during final user acceptance testing, causing rework. The sponsor asks the PM to strengthen the team's approach to preventing defects before they occur, rather than just inspecting the final product. Which activity best addresses the sponsor's request?