Question 96 of 149

A project manager is finalizing the communications approach for a six-month initiative. The executive sponsor wants a concise summary of overall health once a month, while the functional managers who assign resources need detailed weekly updates on task progress and upcoming resource needs. Which document should the project manager use to define who receives which reports, at what frequency, and in what format?