Question 95 of 149

A project manager notices that team members frequently disagree about how proposed changes to deliverables should be submitted, reviewed, and approved. There is no consistent process, so some changes bypass evaluation entirely. Which document should the project manager reference or create to establish how scope will be defined, validated, and controlled throughout the project?