A project manager needs a document that shows the official non-working days, company holidays, and standard working hours that scheduling software should use when calculating task durations and end dates across the project. The team keeps asking why the software pushed several deadlines past dates they assumed would be workdays. Which artifact should the project manager review and update to resolve this?