Midway through a software deployment project, a functional manager asks the project manager to personally write and test several database scripts because the assigned developer is behind schedule. The project manager has coding experience but is already fully occupied coordinating vendors, updating the schedule, and reporting to the sponsor. What is the BEST response for the project manager?