Question 84 of 149
A project manager is finalizing the schedule for a construction project. The team observes several national holidays, works Monday through Friday only, and has a scheduled two-week facility shutdown in July. The project manager wants to ensure the scheduling software accurately reflects when work can actually be performed so that task durations map correctly to real calendar dates. Which document or tool should the project manager configure to capture this information?