During execution of a software migration project, the project manager identifies that a newly released cloud automation tool could dramatically reduce the deployment effort if adopted. The team confirms the benefit is significant, and the PM reassigns the most skilled engineers and adjusts the plan to ensure the project fully captures this benefit. Which risk response strategy is the project manager applying?