A project manager is midway through a 10-month construction project with a total budget of $500,000, spread evenly across the schedule. At the end of month 4, the project should have $200,000 worth of work completed according to the schedule baseline. When preparing a performance report, the PM needs to identify the value of work that was planned to be accomplished by this point in time. Which earned value metric represents this figure?