Question 75 of 149

A project manager is building the schedule for a network installation. Activity A (3 days) is followed by Activity B (5 days), which is followed by Activity D (2 days). A separate path runs Activity A, then Activity C (4 days), then Activity D. Using a forward pass starting at day 0, what is the earliest the project can finish?