A project manager is executing a large infrastructure project. The project sponsor has stated she does not want to receive routine weekly status updates. Instead, she only wants to be notified when a metric exceeds a predefined tolerance, such as a schedule slip beyond 5 days or a cost overrun above 10%. Which reporting approach best satisfies the sponsor's request?