A support team handles a steady stream of unpredictable maintenance requests that arrive individually throughout the day, with no fixed release dates. The project manager wants an approach that visualizes work in progress, limits how many items are worked on at once to avoid overloading the team, and allows continuous delivery as each item completes. Which method best fits these needs?