🔥 3-day streak
CompTIA Project+ (PK0-005)59 / 149
Question 59 of 149

A project manager is planning a data center migration and identifies a risk that a critical hardware component could fail during the cutover, causing extended downtime and significant financial penalties. Rather than attempting to prevent the failure entirely, the PM decides to purchase an insurance policy and a vendor support contract that covers replacement costs and rapid onsite service if the failure occurs. Which risk response strategy is the project manager using?