A project manager is leading a construction project with clearly defined, sequential phases and numerous task dependencies that must be tracked against fixed calendar deadlines. The sponsor wants a visual tool that shows how tasks overlap over time and highlights how a delay in one activity affects downstream work. Which project management tool best meets this need?