🔥 3-day streak
CompTIA Project+ (PK0-005)52 / 149
Question 52 of 149
A project manager is building the schedule for an office relocation. Task B (install network cabling) cannot begin until Task A (complete electrical work) is finished, and Task C (set up workstations) cannot begin until Task B is done. The PM needs a tool that visually displays these task dependencies along a timeline so the team can see how a delay in one task affects the others. Which scheduling tool best meets this need?
Reviewed for accuracy · Report an issueNext question