Question 49 of 149

A project manager is procuring a vendor to build a website with fully documented, unchanging requirements and a firm delivery date. The organization wants to shift the cost risk of the work to the vendor and pay a single predetermined amount regardless of the vendor's actual labor hours. Which contract type best fits this situation?