CompTIA Project+ (PK0-005)48 / 149
Question 48 of 149

A department head proposes a new customer portal and asks the PMO to move forward. Before the sponsor commits funding and signs the charter, the sponsor wants an objective assessment of whether the project is technically achievable, economically justified, and operationally supportable given current staff and systems. Which document should be produced to provide this assessment?