A project manager learns the client moved the go-live date up by three weeks. The design phase is nearly complete, and the budget cannot be increased to add resources or pay overtime. The project manager decides to begin construction activities on the portions of the design that are already approved, rather than waiting for the entire design phase to finish. Which schedule compression technique is being applied?