Question 45 of 149
A project manager is midway through a construction project. The original budget was $500,000, but early performance has been poor, and the team believes the original estimating assumptions no longer apply. The sponsor asks the PM to provide a fresh, bottom-up estimate of how much money will be needed to finish the remaining work. Which forecasting output is the sponsor requesting?