A project manager is halfway through a construction project with a budget at completion (BAC) of $500,000. Current performance data shows the project is running consistently over budget due to higher-than-expected material prices, and this trend is expected to continue for the remainder of the project. The sponsor asks the PM for a realistic forecast of what the total project will cost by the time it is finished. Which calculation should the PM provide?