Question 40 of 149
A project manager is planning a new office relocation and has very little detailed information about the individual tasks. However, the organization completed a nearly identical relocation for a similar department 18 months ago. The PM needs a quick, high-level duration estimate to include in an early planning document. Which estimating technique is MOST appropriate?