🔥 3-day streak
CompTIA Project+ (PK0-005)36 / 149
Question 36 of 149
During planning, a project manager is reviewing the work breakdown structure with the team. A team member notices that the sum of all the deliverables and work packages in the WBS appears to represent slightly more scope than what the approved scope statement authorized. Which WBS principle has been violated?
Reviewed for accuracy · Report an issueNext question