Question 34 of 149
During the closure phase of a facility relocation project, the project manager is holding a final meeting where the customer walks through each delivered workspace against the agreed requirements and signs a document confirming the deliverables meet expectations. After this, the PM plans to archive documents and release the team. Which activity should the PM ensure is completed AFTER obtaining this signature but BEFORE fully closing the project?