Question 25 of 149

A predictive software deployment project is running two weeks behind on a critical-path activity, and the delivery deadline cannot move because it is tied to a contractual milestone. The project manager has budget available and decides to add two experienced developers to the delayed task to bring it back on schedule. Which schedule compression technique is the project manager using?