Halfway through a predictive project, the project manager reviews earned value data. The budget at completion (BAC) is $200,000. The earned value (EV) is $90,000, the actual cost (AC) is $110,000, and the planned value (PV) is $100,000. What does this data tell the project manager about the project's cost performance?