🔥 3-day streak
CompTIA Project+ (PK0-005)23 / 149
Question 23 of 149

A project manager is reviewing earned value data at the end of month three. The earned value (EV) is $180,000 and the actual cost (AC) is $200,000. The sponsor asks whether the project is spending money efficiently relative to the work accomplished. Which calculation should the project manager present, and what does the result indicate?

Reviewed for accuracy · Report an issueNext question