A project manager is reviewing earned value data at the end of month three. The earned value (EV) is $180,000 and the actual cost (AC) is $200,000. The sponsor asks whether the project is spending money efficiently relative to the work accomplished. Which calculation should the project manager present, and what does the result indicate?