Question 21 of 149

A project manager is halfway through the execution phase of a software rollout. During a status review, they compare the actual completion dates of tasks against the dates recorded when the schedule was approved by the sponsor. Several tasks are finishing later than originally documented. Which reference point is the project manager using to measure this timing discrepancy?