CompTIA Project+ (PK0-005)18 / 149
Question 18 of 149

Two engineers on your project disagree about which database technology to use. Rather than picking a side quickly, you gather both engineers, review the performance requirements, benchmark data, and long-term maintenance costs together, then reach a decision supported by the evidence. Which conflict resolution technique are you using?