Question 17 of 149
Two functional managers on a project disagree over how a shared testing lab should be scheduled. Neither will get full access to the lab during the critical testing window. After discussion, the project manager helps them agree that each team gets the lab for half the available days, with both giving up some of what they originally wanted so the project can move forward. Which conflict resolution technique did the project manager use?