CompTIA Project+ (PK0-005)16 / 149
Question 16 of 149
A vendor supporting your project has informed you verbally that they need to adjust a contractual deliverable date that will affect the project's legally binding agreement. As the project manager, you need to document this change and ensure both organizations have an official, authoritative record for potential future disputes. Which communication method is MOST appropriate?
Reviewed for accuracy · Report an issueNext question